§ 05Sheet 05 / PlanningEstimates, formulas shown

Plan the laundry room

Size the washers from the pounds you wash, check the room against what washer-extractors need, and see the order an installation runs in.

  1. 05.1Capacity planner
  2. 05.2Laundry room checklist
  3. 05.3Installation sequence
On-premises laundry with a washer-extractor, tumble dryers, and wire linen carts
Fig. 01Washer, dryers, and carts share one room. The layout decides how fast goods move between them.
§ 05.1Capacity plannerTool T-01

Pounds per day, into machines.

An estimate to start the conversation, not a specification. Washer capacity is rated by the dry weight of the goods.

lb
h
min
%

Time lost to loading, unloading, sorting, and breaks. Set 100% to ignore it.

Split across

At least two machines, so the laundry keeps running when one is being serviced.

Pounds per hour needed

150lb/h

Loads per hour, each machine

1.13loads

Washer capacity per cycle, total

132lb dry

Suggested size, each machine

66lb dry

Round each machine up to the next available capacity. Peaks, mixed goods, and formulas with long rinses all call for more margin.

§ 05.2Laundry room checklist8 items

Check the room before the machine.

Most installation delays trace back to one of these eight items. The machine's installation manual sets the exact values.

Washer-extractor with its door open beside a cart of white towels
Fig. 02Room for carts in front of the door matters as much as room behind the machine.

Water supply

Hot and cold lines sized for fast fills, with a shutoff at each machine.

  • Pressure within the range in the installation manual. Too low slows every fill; too high invites water hammer.
  • Backflow protection where local code requires it.

Drains

Washer-extractors dump a full bath at once, so drains are sized for flow, not just pipe size.

  • Gravity drain to a trench or sump; a surge tank and pump where gravity drainage is not possible.
  • The International Plumbing Code (Sec. 1003.6) requires commercial washers to discharge through an interceptor with a removable basket that stops solids 1/2 inch or larger, string, rags, and buttons. Check local amendments.

Electrical

Voltage and phase to match each machine's nameplate. Electrically heated machines are often three-phase.

  • An individual branch circuit for each machine, not shared with lighting or other equipment.
  • Work by a licensed electrician.

Ventilation

Washers add heat and humidity; dryers add much more.

  • Dryers exhaust to the outdoors.
  • The International Mechanical Code calls for makeup air where dryer exhaust exceeds 200 cfm.

Floor and foundation

The mounting type decides the floor.

  • Hard-mount: reinforced concrete built to the manufacturer's foundation specification, with anchor bolts and grout, usually at ground level.
  • Soft-mount: usually no anchors or special foundation, but a level floor strong enough for the static and dynamic loads, confirmed by a structural engineer.

Door widths and delivery path

Measure the narrowest point of the whole route, not just the laundry room door.

  • Doorways, corridors, turns, ramps, and elevators against the machine's crated and uncrated dimensions.
  • Elevator and floor load ratings against the machine's shipping weight.

Service clearance

Leave the clearance the installation manual specifies behind and beside each machine. Published rear clearances are often around 20 inches.

  • Room to remove panels and reach the drain valve, belts, and motor.
  • Room in front for carts, loading, and unloading.

Chemical dosing

Plan the chemistry with the room, not after it.

  • Wall space for dosing pumps near the machines, and a route for chemical lines.
  • Chemical storage with spill containment, away from walkways.
§ 05.3Installation sequence8 steps

From survey to first load.

The order most washer-extractor installations follow. A hard-mount installation adds a foundation and its curing time.

  1. Site survey

    Measure the room and the delivery path, record the existing water, drain, power, and venting, and note the floor type and level.

  2. Sizing and layout

    Turn pounds per day into capacity and machine count, then draw the layout with clearances, cart space, and utility points.

  3. Utility rough-in

    Water lines and shutoffs, drains with the trench or sump and interceptor, electrical circuits, dryer venting, and dosing pump locations.

  4. Foundation, if hard-mount

    Reinforced concrete to the manufacturer's specification with anchor positions set, then the curing time the foundation design calls for.

  5. Delivery and rigging

    Move each machine along the measured path with the right equipment, protecting floors, doorways, and elevators.

  6. Setting

    Level each machine. Anchor and grout hard-mount machines. Remove the shipping restraints from soft-mount machines before the first run.

  7. Connections

    Water and drain connections, power by a licensed electrician, and chemical lines by the chemical supplier.

  8. Commissioning and training

    Test cycles, interlock and safety checks, formulas set with the chemical supplier, and operator training before handover.

    What commissioning covers
§ 05.4Send your plan

Send us the room.

A sketch or photos of the room, the planner's numbers, and what is on the floor today. We will reply by email with what to check next.